LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
20INR0202 · Solar · Bosque County

Rueter Solar

Withdrawn

Rueter Solar is a 200 MW solar project in Bosque County, Texas, with no point of interconnection listed. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
20INR0202
Capacity
200 MW
Fuel
Solar
Substation
Not listed
Interconnecting entity
Not listed
Projected COD
n/a
Entered queue
11/01/2022
ERCOT zone
n/a
Size category
n/a

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 11/01/2022
    Listed as inactive

Other projects at this substation

No other projects at this substation.