19INR0100 · Wind · Mclennan County

Prairie Hill Wind

Prairie Hill Wind is a 297 MW wind project in Mclennan County, Texas, connecting at tap 345kV 3405 Tradinghouse - 3402 Lake Creek. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 09/30/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
19INR0100
Capacity
297 MW
Fuel
Wind (WT)
Interconnecting entity
Prairie Hill LLC
Projected COD
09/30/2027
Entered queue
06/19/2017
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 11/12/2020
    Energization Approved → Sync Approved
  • 10/19/2020
    IA Signed → Energization Approved
  • 04/03/2020
    FIS Requested → FIS Approved
  • 09/17/2018
    FIS Approved → IA Signed
  • 06/19/2017
    Entered the queue with 297 MW, projected COD 09/30/2027
  • 06/19/2017
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.