Counties / Texas
Sutton County power projects
Sutton County, Texas has 2 active power projects totalling 307 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 307 MW (100%). The largest single project is Sonora High Noon BESS (204 MW battery storage). 0 projects have signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.
Active projects
2
0.3 GW capacity
IA signed or later
0
0% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
1
since Sep 2026
Changes in Sutton County
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Sonora High Noon BESS | BESS | 204 | 60412 CARVER 138kV | FIS Requested | 07/01/2028 |
| Atticus Energy Storage | BESS | 103 | Tap 69 KV 6570 Bond Road - 6513 Sonora | FIS Requested | 01/26/2030 |
| Axis Ridge Wind | Wind | 392 | 60210 Friess Ranch 138KV | Withdrawn | 03/19/2030 |
For residents and landowners
- What power projects are planned in Sutton County?
- ERCOT's October 2026 report lists 2 active projects in Sutton County totalling 307 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.