LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Rockwall County power projects

Rockwall County, Texas has 1 active power project totalling 125 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 125 MW (100%). The largest single project is TE Smith Storage 2 (125 MW battery storage). 0 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
1
0.1 GW capacity
IA signed or later
0
0% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
1
since Sep 2026

Changes in Rockwall County

COD change
10/01/2026
TE Smith Storage 2 · BESS · Rockwall County
Projected COD moved 08/16/2027 → 02/07/2029. Delay #1 for this project.
+18 mo

All projects

ProjectFuelMWSubstationStageCOD
TE Smith Storage 2BESS1252478 Royse 345kVFIS Requested02/07/2029

For residents and landowners

What power projects are planned in Rockwall County?
ERCOT's October 2026 report lists 1 active project in Rockwall County totalling 125 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.