Chambers County power projects
Chambers County, Texas has 3 active power projects totalling 1,069 MW in ERCOT's interconnection queue as of the October 2026 report. Natural gas is the largest share at 697 MW (65%). The largest single project is Cedar Bayou 5 (TEF - Due Diligence) (697 MW natural gas). 3 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
3
1.1 GW capacity
IA signed or later
3
100% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
1
since Sep 2026
Changes in Chambers County
COD change
10/01/2026
Cedar Bayou 5 (TEF - Due Diligence) · Gas · Chambers County
Projected COD moved 12/15/2027 → 03/31/2028. Delay #1 for this project.
+4 mo
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Cedar Bayou 5 (TEF - Due Diligence) | Gas | 697 | 40000 Cedar Bayou 345kV | IA Signed | 03/31/2028 |
| APV Plumwood Storage | BESS | 201 | Tap 138kV 40171 Baytown - 40015Cedar Bayou Plant | IA Signed | 10/01/2029 |
| Coneflower Storage Project | BESS | 171 | 40855 JORDON 138 kV | IA Signed | 02/28/2028 |
For residents and landowners
- What power projects are planned in Chambers County?
- ERCOT's October 2026 report lists 3 active projects in Chambers County totalling 1,069 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.