Chambers County power projects

Chambers County, Texas has 3 active power projects totalling 1,069 MW in ERCOT's interconnection queue as of the October 2026 report. Natural gas is the largest share at 697 MW (65%). The largest single project is Cedar Bayou 5 (TEF - Due Diligence) (697 MW natural gas). 3 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
3
1.1 GW capacity
IA signed or later
3
100% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
1
since Sep 2026

Changes in Chambers County

COD change
10/01/2026
Cedar Bayou 5 (TEF - Due Diligence) · Gas · Chambers County
Projected COD moved 12/15/2027 → 03/31/2028. Delay #1 for this project.
+4 mo

All projects

For residents and landowners

What power projects are planned in Chambers County?
ERCOT's October 2026 report lists 3 active projects in Chambers County totalling 1,069 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.