Substation / point of interconnection ยท Zapata County
Tap 345 kV 80225 CENIZO7C - 80307 DELSOL7C
2 active projects totalling 500 MW are queued to connect at Tap 345 kV 80225 CENIZO7C - 80307 DELSOL7C in Zapata County, Texas, according to ERCOT's October 2026 report.
Active capacity
500 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 30INR0042 | La Morena Energy Center BESS | BESS | 250 | Screening | 05/07/2029 | 0 |
| 30INR0043 | La Morena Energy Center Solar | Solar | 250 | Screening | 05/07/2029 | 0 |