Substation / point of interconnection ยท Zapata County
Tap 138kV 8299 Zapata - 8957 Lopeno
1 active project totalling 201 MW is queued to connect at Tap 138kV 8299 Zapata - 8957 Lopeno in Zapata County, Texas, according to ERCOT's October 2026 report.
Active capacity
201 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0116 | Falcon Zapata Storage 138 | BESS | 201 | IA Signed | 03/11/2028 | 0 |