Tap 138kV #1450 Pleasant Valley Switch - #1492 Wichita Falls Riverbend
1 active project totalling 203 MW is queued to connect at Tap 138kV #1450 Pleasant Valley Switch - #1492 Wichita Falls Riverbend in Wichita County, Texas, according to ERCOT's October 2026 report.
Active capacity
203 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0472 | Bologna BESS | BESS | 203 | FIS Approved | 04/19/2028 | 0 |