LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Wharton County

tap of 138kV 8750 Chalmers - 8127 Lane City

2 active projects totalling 267 MW are queued to connect at tap of 138kV 8750 Chalmers - 8127 Lane City in Wharton County, Texas, according to ERCOT's October 2026 report.

Active capacity
267 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
28INR0160Neal SolarSolar147FIS Requested04/03/20290
28INR0452Neal BatteryBESS120FIS Requested04/03/20290