LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection · Wharton County

tap Blue – Hillje 345 kv Ckt.#27

3 active projects totalling 661 MW are queued to connect at tap Blue – Hillje 345 kv Ckt.#27 in Wharton County, Texas, according to ERCOT's October 2026 report.

Active capacity
661 MW
queued at this substation
Active projects
3
3 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
21INR0220Maleza SolarSolar255IA Signed12/31/20280
23INR0227Maleza Solar IISolar255FIS Requested12/31/20280
21INR0456Maleza StorageBESS151FIS Requested12/31/20280