Substation / point of interconnection ยท Wharton County
Tap 138kV 42985 DYANN_POI8 - 43190 S_LANE_B138 Ckt 60
1 active project totalling 101 MW is queued to connect at Tap 138kV 42985 DYANN_POI8 - 43190 S_LANE_B138 Ckt 60 in Wharton County, Texas, according to ERCOT's October 2026 report.
Active capacity
101 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0545 | Blue Creek Energy Storage | BESS | 101 | FIS Requested | 12/31/2028 | 0 |