Substation / point of interconnection ยท Wharton County
Line Tap 138kV #43012 NEWGLF60T3_8 - #43190 S_LANE_B138
1 active project totalling 101 MW is queued to connect at Line Tap 138kV #43012 NEWGLF60T3_8 - #43190 S_LANE_B138 in Wharton County, Texas, according to ERCOT's October 2026 report.
Active capacity
101 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0569 | Hadrian Energy Storage | BESS | 101 | FIS Approved | 12/31/2028 | 0 |