Substation / point of interconnection ยท Wharton County
44880 Waterh_POI_5 345kV
5 active projects totalling 757 MW are queued to connect at 44880 Waterh_POI_5 345kV in Wharton County, Texas, according to ERCOT's October 2026 report.
Active capacity
757 MW
queued at this substation
Active projects
5
5 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0725 | PHOTON BESS REPOWERING | BESS | 306 | FIS Approved | 08/17/2027 | 0 |
| 25INR0493 | PHOTON SOLAR 1 2 SLF | Solar | 236 | Sync Approved | 05/11/2026 | 0 |
| 23INR0111 | PHOTON SOLAR 3 SLF | Solar | 110 | Sync Approved | 05/11/2026 | 0 |
| 25INR0673 | PHOTON SOLAR 4 SLF | Solar | 106 | Sync Approved | 05/11/2026 | 0 |
| 26INR0718 | PHOTON SOLAR REPOWERING | Solar | 0 | IA Signed | 08/17/2027 | 0 |