LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Wharton County

44220 Julia 345kV

1 active project totalling 256 MW is queued to connect at 44220 Julia 345kV in Wharton County, Texas, according to ERCOT's October 2026 report.

Active capacity
256 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
25INR0582Maleza Storage IIBESS256FIS Requested12/31/20280