Substation / point of interconnection ยท Wharton County

44200 Hillje 345kV

4 active projects totalling 1,519 MW are queued to connect at 44200 Hillje 345kV in Wharton County, Texas, according to ERCOT's October 2026 report.

Active capacity
1,519 MW
queued at this substation
Active projects
4
4 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
20INR0069Danish Fields SolarSolar603Sync Approved08/29/20260
21INR0505Ramsey StorageBESS500IA Signed06/30/20280
21INR0341Space City SolarSolar366IA Signed06/01/20270
20INR0238Voyager StorageBESS50FIS Requested04/08/20280