Substation / point of interconnection ยท Starr County
TAP 138KV 8793 RIO GRANDE CITY - 8798 LAGRULLA
1 active project totalling 200 MW is queued to connect at TAP 138KV 8793 RIO GRANDE CITY - 8798 LAGRULLA in Starr County, Texas, according to ERCOT's October 2026 report.
Active capacity
200 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0445 | PSE Flores TX Storage | BESS | 200 | FIS Requested | 06/30/2028 | 0 |