Substation / point of interconnection ยท Schleicher County
Tap 138 kV Live Oak (6500) - Santiago (6490)
1 active project totalling 82 MW is queued to connect at Tap 138 kV Live Oak (6500) - Santiago (6490) in Schleicher County, Texas, according to ERCOT's October 2026 report.
Active capacity
82 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0150 | Proving Ground Solar | Solar | 82 | FIS Requested | 06/30/2028 | 0 |