Substation / point of interconnection · Rusk County
Mt. Enterprise (Bus # 3116) – Martin Lake 345kv Line (Bus # 3100
1 active project totalling 302 MW is queued to connect at Mt. Enterprise (Bus # 3116) – Martin Lake 345kv Line (Bus # 3100 in Rusk County, Texas, according to ERCOT's October 2026 report.
Active capacity
302 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 22INR0332 | Brantley Branch Batt | BESS | 302 | FIS Requested | 02/01/2029 | 0 |