Substation / point of interconnection ยท Runnels County
Tap to the 345kV Odysseus (Bus#60072) to Bluff Creek (Bus #60040) line
1 active project totalling 201 MW is queued to connect at Tap to the 345kV Odysseus (Bus#60072) to Bluff Creek (Bus #60040) line in Runnels County, Texas, according to ERCOT's October 2026 report.
Active capacity
201 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0210 | Sawtooth Solar | Solar | 201 | FIS Requested | 08/01/2030 | 0 |