Substation / point of interconnection ยท Reeves County
Tap 345 kV 60404 SOLSTICE - 11098 SANDLAKE_5
2 active projects totalling 1,031 MW are queued to connect at Tap 345 kV 60404 SOLSTICE - 11098 SANDLAKE_5 in Reeves County, Texas, according to ERCOT's October 2026 report.
Active capacity
1,031 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0468 | Glass Mountain Wind 2 | Wind | 519 | FIS Requested | 12/31/2028 | 0 |
| 29INR0194 | Glass Mountain Wind 1 | Wind | 512 | FIS Requested | 12/31/2028 | 0 |