Substation / point of interconnection ยท Reeves County
60716 Saragosa 138kV
2 active projects totalling 545 MW are queued to connect at 60716 Saragosa 138kV in Reeves County, Texas, according to ERCOT's October 2026 report.
Active capacity
545 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 23INR0116 | Cantaloupe Solar | Solar | 307 | IA Signed | 07/01/2028 | 0 |
| 26INR0034 | Bracero Pecan Storage | BESS | 238 | IA Signed | 07/01/2027 | 0 |