Substation / point of interconnection ยท Red River County
Tap the 69 kV Bagwell (#1785) - Clarksville (#11784) line, ONCOR
2 active projects totalling 75 MW are queued to connect at Tap the 69 kV Bagwell (#1785) - Clarksville (#11784) line, ONCOR in Red River County, Texas, according to ERCOT's October 2026 report.
Active capacity
75 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
69 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0292 | Donelson Solar SLF | Solar | 75 | FIS Requested | 10/17/2028 | 0 |
| 27INR0293 | Donelson Storage SLF | BESS | 0 | FIS Requested | 10/17/2028 | 0 |