Substation / point of interconnection · Reagan County
Tap 345kV 59903 Bearkat – 76000 NORTMC5_1Y; Badger 345 kV Station
1 active project totalling 310 MW is queued to connect at Tap 345kV 59903 Bearkat – 76000 NORTMC5_1Y; Badger 345 kV Station in Reagan County, Texas, according to ERCOT's October 2026 report.
Active capacity
310 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0042 | Slager Lake Wind | Wind | 310 | IA Signed | 07/01/2029 | 0 |