LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Rains County

tap 138kV Emory North 3171 to Liberty POD 1723

1 active project totalling 176 MW is queued to connect at tap 138kV Emory North 3171 to Liberty POD 1723 in Rains County, Texas, according to ERCOT's October 2026 report.

Active capacity
176 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
25INR0370Willis StorageBESS176IA Signed05/31/20280