Substation / point of interconnection · Pecos County
Tap TNMP White Baker (38435)–Bottlebrush(38441) 345-kV double-circuit
3 active projects totalling 3,009 MW are queued to connect at Tap TNMP White Baker (38435)–Bottlebrush(38441) 345-kV double-circuit in Pecos County, Texas, according to ERCOT's October 2026 report.
Active capacity
3,009 MW
queued at this substation
Active projects
3
3 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
n/a
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 31INR0019 | Permian I Natural Gas | Gas | 1,247 | FIS Requested | 06/30/2030 | 0 |
| 31INR0018 | Permian I Solar | Solar | 1,126 | FIS Requested | 06/30/2030 | 0 |
| 30INR0086 | Permian I Wind | Wind | 636 | FIS Requested | 06/30/2030 | 0 |