Substation / point of interconnection ยท Pecos County
Tap 345 kV 60404 SOLSTICE - 11098 SANDLAKE_5
2 active projects totalling 603 MW are queued to connect at Tap 345 kV 60404 SOLSTICE - 11098 SANDLAKE_5 in Pecos County, Texas, according to ERCOT's October 2026 report.
Active capacity
603 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0182 | Pecos Flats Solar II | Solar | 302 | FIS Requested | 02/05/2029 | 0 |
| 29INR0183 | Pecos Flats Solar III | Solar | 302 | FIS Requested | 02/05/2029 | 0 |