Substation / point of interconnection ยท Pecos County
Solstice Substation #60384 -AEP
1 active project totalling 500 MW is queued to connect at Solstice Substation #60384 -AEP in Pecos County, Texas, according to ERCOT's October 2026 report.
Active capacity
500 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
n/a
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 30INR0053 | MRR Solar | Solar | 500 | IA Signed | 07/01/2030 | 0 |