LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Pecos County

860 GIRVINSW 345kV

2 active projects totalling 154 MW are queued to connect at 860 GIRVINSW 345kV in Pecos County, Texas, according to ERCOT's October 2026 report.

Active capacity
154 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
29INR0324Ashtrom Marigold BESS SLFBESS154FIS Requested04/26/20290
26INR0715Tierra Bonita BESS SLFBESS0FIS Requested06/01/20290