Substation / point of interconnection ยท Pecos County
60718 Pecos Valley 138kV
1 active project totalling 309 MW is queued to connect at 60718 Pecos Valley 138kV in Pecos County, Texas, according to ERCOT's October 2026 report.
Active capacity
309 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 22INR0365 | Mensa BESS | BESS | 309 | FIS Requested | 06/01/2028 | 0 |