Substation / point of interconnection ยท Pecos County
60404 SOLSTICE 345 kV
1 active project totalling 302 MW is queued to connect at 60404 SOLSTICE 345 kV in Pecos County, Texas, according to ERCOT's October 2026 report.
Active capacity
302 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0181 | Pecos Flats Solar | Solar | 302 | FIS Requested | 10/20/2029 | 0 |