LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Nueces County

85000 Nelson Sharpe 345kV

2 active projects totalling 220 MW are queued to connect at 85000 Nelson Sharpe 345kV in Nueces County, Texas, according to ERCOT's October 2026 report.

Active capacity
220 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
23INR0061Noria Solar DCCSolar145IA Signed04/21/20280
23INR0062Noria StorageBESS75IA Signed04/21/20280