LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Nueces County

5640 DRISCOLLSUB9 69kV

1 active project totalling 151 MW is queued to connect at 5640 DRISCOLLSUB9 69kV in Nueces County, Texas, according to ERCOT's October 2026 report.

Active capacity
151 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
69 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
26INR0222GOTHAM BESSBESS151FIS Requested03/17/20270