Substation / point of interconnection ยท Nolan County
1338 Eskota 138kV
1 active project totalling 6.4 MW is queued to connect at 1338 Eskota 138kV in Nolan County, Texas, according to ERCOT's October 2026 report.
Active capacity
6.4 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 17INR0069 | Trent repower | Wind | 6 | Sync Approved | 01/01/2026 | 0 |