LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Navarro County

Tapping 138 kV line Telico (192) to Montfort Switch (3454)

1 active project totalling 146 MW is queued to connect at Tapping 138 kV line Telico (192) to Montfort Switch (3454) in Navarro County, Texas, according to ERCOT's October 2026 report.

Active capacity
146 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
24INR0205Wensowitch SolarSolar146FIS Approved04/17/20291