2 active projects totalling 619 MW are queued to connect at tap 345kV 1906 Venus - 68091 Navarro in Navarro County, Texas, according to ERCOT's October 2026 report.

Active capacity
619 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
22INR0437TORMES SOLARSolar357IA Signed03/31/20270
25INR0018Yellow Cat WindWind262IA Signed03/05/20270