Substation / point of interconnection ยท Milam County
(3707) Cannon Switch 138kV
1 active project totalling 207 MW is queued to connect at (3707) Cannon Switch 138kV in Milam County, Texas, according to ERCOT's October 2026 report.
Active capacity
207 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 23INR0235 | Hoyte Solar | Solar | 207 | IA Signed | 04/15/2027 | 0 |