LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Milam County

3377 LTPSW 345KV

1 active project totalling 600 MW is queued to connect at 3377 LTPSW 345KV in Milam County, Texas, according to ERCOT's October 2026 report.

Active capacity
600 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
26INR0609Scorpius SolarSolar600FIS Requested06/14/20290