Substation / point of interconnection ยท Milam County
138kV Tap 3675 Rogers - 3485 Tin Roof Pod
1 active project totalling 232 MW is queued to connect at 138kV Tap 3675 Rogers - 3485 Tin Roof Pod in Milam County, Texas, according to ERCOT's October 2026 report.
Active capacity
232 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 23INR0468 | Petunia Storage Project | BESS | 232 | FIS Requested | 06/30/2028 | 0 |