Substation / point of interconnection ยท Midland County
11165 Sloan Switch 138kV
1 active project totalling 18 MW is queued to connect at 11165 Sloan Switch 138kV in Midland County, Texas, according to ERCOT's October 2026 report.
Active capacity
18 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 23INR0300 | Holzer Solar | Solar | 18 | Sync Approved | 11/16/2026 | 0 |