Substation / point of interconnection ยท Maverick County

8692 MAVERICK4A 138kV

1 active project totalling 202 MW is queued to connect at 8692 MAVERICK4A 138kV in Maverick County, Texas, according to ERCOT's October 2026 report.

Active capacity
202 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0253Old Victory Energy CenterBESS202FIS Requested06/01/20300