ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Matagorda County

#8754 Zoisite 345kV

3 active projects totalling 1,006 MW are queued to connect at #8754 Zoisite 345kV in Matagorda County, Texas, according to ERCOT's October 2026 report.

Active capacity
1,006 MW
queued at this substation
Active projects
3
3 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0141Bluefox Solar 1Solar403FIS Requested05/31/20290
28INR0063Bluefox Solar 2Solar402FIS Requested01/17/20300
28INR0064Bluefox Solar 3Solar202FIS Requested04/18/20300