Substation / point of interconnection ยท Matagorda County
8111 MAGILL4A 138KV
1 active project totalling 143 MW is queued to connect at 8111 MAGILL4A 138KV in Matagorda County, Texas, according to ERCOT's October 2026 report.
Active capacity
143 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0271 | City Breeze BESS | BESS | 143 | IA Signed | 03/18/2027 | 0 |