LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Matagorda County

29.188382, -95.911558

1 active project totalling 9.5 MW is queued to connect at 29.188382, -95.911558 in Matagorda County, Texas, according to ERCOT's October 2026 report.

Active capacity
9.5 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
n/a
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
25INR0604Pledger BESSBESS10IA Signed11/04/20260