Substation / point of interconnection ยท Live Oak County

5690 WEST GEORGE WEST SUB 69kV

2 active projects totalling 82 MW are queued to connect at 5690 WEST GEORGE WEST SUB 69kV in Live Oak County, Texas, according to ERCOT's October 2026 report.

Active capacity
82 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
69 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0375Buck Ranch Solar SLFSolar41FIS Requested08/02/20280
27INR0376Buck Ranch Storage SLFBESS41FIS Requested08/09/20280