Substation / point of interconnection ยท Leon County
Tap 345kV 967 GIBN_CREK_5 - 46020 LIMEST_POI_5 Ckt 18 and 345kV 79007 YELLOW WOLF - 46020 LIMEST_POI_5 Ckt 50
1 active project totalling 1,981 MW is queued to connect at Tap 345kV 967 GIBN_CREK_5 - 46020 LIMEST_POI_5 Ckt 18 and 345kV 79007 YELLOW WOLF - 46020 LIMEST_POI_5 Ckt 50 in Leon County, Texas, according to ERCOT's October 2026 report.
Active capacity
1,981 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 30INR0091 | BM Great Rock Energy Center | Gas | 1,981 | FIS Requested | 05/15/2029 | 0 |