LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Kent County

Tap 345 kV Nova prime (BUS# 59908) to Mhos (BUS# 59911)

2 active projects totalling 486 MW are queued to connect at Tap 345 kV Nova prime (BUS# 59908) to Mhos (BUS# 59911) in Kent County, Texas, according to ERCOT's October 2026 report.

Active capacity
486 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
29INR0394Buzzer Butte SolarSolar243FIS Requested09/01/20300
30INR0164Buzzer Butte 2 SolarSolar243FIS Requested09/01/20300