Substation / point of interconnection ยท Kent County
59908 Novaprime 345kV
2 active projects totalling 511 MW are queued to connect at 59908 Novaprime 345kV in Kent County, Texas, according to ERCOT's October 2026 report.
Active capacity
511 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0447 | Jay Flat BESS | BESS | 259 | FIS Requested | 02/13/2029 | 0 |
| 27INR0435 | Clairemont Solar 1 | Solar | 252 | IA Signed | 02/13/2029 | 0 |