Substation / point of interconnection ยท Kaufman County
Tap 138kV 2727 CRANDALL1_8 - 2724 KAUFMN_8
1 active project totalling 206 MW is queued to connect at Tap 138kV 2727 CRANDALL1_8 - 2724 KAUFMN_8 in Kaufman County, Texas, according to ERCOT's October 2026 report.
Active capacity
206 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0412 | Yellow Leaf II BESS | BESS | 206 | FIS Requested | 09/25/2028 | 0 |