Substation / point of interconnection ยท Howard County
Tap 345kV 10057 Prong Moss Switch - 10062 Rockhound Switch CKT 1
1 active project totalling 205 MW is queued to connect at Tap 345kV 10057 Prong Moss Switch - 10062 Rockhound Switch CKT 1 in Howard County, Texas, according to ERCOT's October 2026 report.
Active capacity
205 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0629 | Midland Energy Storage | BESS | 205 | FIS Requested | 06/09/2029 | 0 |