Substation / point of interconnection ยท Howard County
Natural Dam 138kV Substation (23836)
1 active project totalling 205 MW is queued to connect at Natural Dam 138kV Substation (23836) in Howard County, Texas, according to ERCOT's October 2026 report.
Active capacity
205 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0485 | Prospector Energy Storage | BESS | 205 | FIS Requested | 09/30/2026 | 0 |